Tuesday, May 26, 2009

After the rain














Brisbane received 1/3 of its annual rainfall last week, which clashed with the planned installation of the roof sheeting.













Plumbing and electrical have gone in, however, with copper piping for internal water supply. The alternative was recycled poly pipe but copper prices had dropped since the start of the project and is 60% recycled, with a long life-span.

Site foreman, Oliver, has been fabricating the sunshading awning frames on site. These awnings, to all windows without adequate roof protection or needing extra shading, will be topped with painted compressed fibre cement sheeting.
The base of the steel stand for the greywater treatment tanks was cut out of the centre of a diamond-tipped saw blade.