After delays due to forecast storms, the rear lower slab was finally poured using the Magnesium Oxide. The additional aggregate for the final terrazzo-like finish made the mix a challenge to pump. In the end, human power prevailed. The slab has been sealed and won't be ground and polished until it is well protected by the floor above.
Blockwork walls to the front have been core-filled with magnesium oxide concrete mix. Blockwork walls to the lower level will begin today.
Once approval from our clients is given for the varied colours of bluestone, sourced from Yatala, the stone walls will start.