Monday, November 2, 2009

A splash of colour


Cheerful, singing Rudy and his team of painters is now adding colour to the interiors.



Blockwork internally will receive a final coat or three of natural limewash paint. The lower floor is now complete but the main floor is next.

The soffit lining to the entry is a combination of the original home's hoop pine flooring and black-stained hardwood.

Tuesday, October 27, 2009

Rains and tanks

Photos above by Marcelo
A fantastic storm last night started to fill the two 23,000L rainwater tanks beneath the front yard.. and the surrounding soil.

The builder's concern with the tanks is their risk of "floating" when surrounding soil gets water-logged and the tank water volume is insufficient to counteract the pressure, pushing the tanks upward. The ideal topping currently nominated is a recycled plastic grid holding finely crushed recycled brick and concrete gravel, allowing water to permeate the soil around the tanks and into the water table. The current recommendation from the builder and tank installer is to weigh the tanks down with a concrete driveway.

Limewash painting is almost complete and the VOC-free Queensland-made paint is brightening up the interior.
The timber screen to the courtyard, which will give privacy on both sides of the fence, will be constructed of timber from the original house. Recycled timber decking palings will be fixed to the hardwood rails, on the taper-chamfered posts. The recycled laminated beam supports to the River Terrace roof have been stained, oiled and meticulously flashed to protect them from the elements.

Tuesday, October 13, 2009

Big hole

The last two tanks (47,000L) will be lowered into place tomorrow in the front of the house. This will make the total rainwater storage capacity to around 60,000L - sufficient to run the house and garden.
The last wall to be rendered is now complete and the natural limewash finish is underway externally. This wall will receive a natural clay and plant fibre render finish.

Saturday, October 10, 2009

Latest progress

Wall linings are almost complete using the high-recycled content "plasterboard" and recycled vj linings from the old house. Balconies are being lined beneath to provide weather protection to the spaces below. The front trellis is underway to the balcony - constructed from reycled hardwood, with deciduous vines to be grown over to extend shade in summer time.

Monday, September 21, 2009

Most of the external painting, with the exception of the blockwork is painted in VOC-free paint by the cheerful, singing painters. Lightweight cladding is in two tones of soft green, broken by bands of galvanised flashing.






One of the pavers cast with the flooring concrete has been polished to give an idea of the finish to internal floors. External surfaces will have less polish for safety reasons, particularly around the pool. Internal vj linings from the original house are now complete. These will be painted over for a more consistent look but it is hoped that a feature section in the Living Room will be retained with a clear seal as a historical reference to the old home.

Wednesday, September 16, 2009

Scaffolding down and student tour

Scaffolding has come down on the outside of the building, revealing more of the building with its fresh coat of VOC-free paint, manufactured in southeast Queensland.

The large cantilevered pelmet for the sunshading venetian blind is constructed from the same laminated hardwood beams as the floor joists in the house. In their former life, they supported the weightlifting floor at the Commonwealth Games in Brisbane in 1982.



Three groups of UQ students visited the site in the afternoon to learn about sustainable construction. This is a good warm up to many future tours of the building and gardens.

The days are nearing the Spring Equinox (22nd September this year), the date when roof and awning overhangs are designed to start cutting out the direct, warmer sun. With only a week to go, this is clearly evident in the photo below (taken at noon) on the northern balcony to the street. A dediduous, leafy trellis will extend shade out over the balcony for summer time living.

Glass and stainless balustrades have now gone in to the rear. A little prematurely but will provide better safety for workers on site.









Carpenter Damian Stapleton, very happy to be working on the job!

Formwork removed from cast concrete garden seat, render to block base and recycled timber post from original home.

Tuesday, September 1, 2009

More recycled trees

Ceiling lining continues in the front bedrooms, using the vj boards from the old house and other salvaging sources.

Blockwork internally and externally will be rendered and finished in a natural lime paint.

Photos by Marcelo Garcia

Monday, August 31, 2009

August update


I've returned from 3 months' leave visiting inspiring and thought-provoking building projects in Canada and the US, under pedal power (www.esdcycle.blogspot.com). Work on the Hill End Ecohouse has progressed dramatically under an increasing team of people, with spaces taking shape and all window joinery in (local plantation hoop pine and hardwood).
Cladding is almost complete - a combination of recycled hardwood weatherboards and FC custom weather boards. The fins to the rear balconies have been clad in the offcuts of the balcony decking hardwood and clear-finished.
The ventilated skin of cladding to the western wall is now complete. Cladding is packed out from the main studs and insulated sisalation, with bird mesh at the top and bottom. You can see the airspace beneath the mini orb soffit, below.